T-ZERO Launch tracker

Artemis: announced vs achieved

NASA · last verified 2026-10-02

NASA's program to return astronauts to the Moon with the SLS rocket and Orion capsule plus commercial landers. Artemis II flew a crewed lunar flyby in April 2026; the schedule for the first landing was restructured in February 2026.

Claims tracked
5
Achieved
2
On track
1
Slipped
2
Dropped
0
Unknown
0
Met on original date
0% (0 of 4 decided)
Average delay where late
33 months

Timeline of claims

Timeline key: dot = announced, diamond = original target, coloured dot = outcome or current target, dashed line = today.

NASA: End of 2017

AchievedArtemis

First flight of the Space Launch System (SLS) heavy-lift rocket by the end of 2017, as announced when NASA unveiled the design.

Announced
Original target
End of 2017
Achieved
Nov 16, 2022
Months late
Delivered 59 months after the original target
Source confidence
Primary or official source checked
Last verified

Artemis I flew uncrewed on Nov 16, 2022 and lasted about 25 days. Interim dates were revised several times between 2011 and 2022; only the original target is shown here.

NASA: By 2024

SlippedArtemis

Return American astronauts to the Moon by 2024 (US Vice President Pence, relaying the White House policy; NASA accepted the goal).

Short quote: “within the next five years”

Announced
Original target
By 2024
Current target
February 2028 (NASA now targets early 2028 for the first crewed Artemis landing (Artemis IV))
Months late
Current target is 38 months after the original
Source confidence
Primary or official source checked
Last verified

The 2024 goal was later replaced by 2025, then September 2026 (art-2), then 2027, and now 2028. Artemis III is now a 2027 Earth-orbit docking test with commercial landers, not a landing.

NASA: November 2024

AchievedArtemis

Artemis II, the first crewed Orion flight around the Moon, launching in November 2024 (the date before NASA's January 2024 move to September 2025).

Announced
(date of the NASA release that restates the Nov 2024 target)
Original target
November 2024
Achieved
Apr 1, 2026
Months late
Delivered 17 months after the original target
Source confidence
Primary or official source checked
Last verified

Launched April 1, 2026 from Pad 39B; splashdown April 10, 2026 after a lunar flyby. Interim targets: Sept 2025 (Jan 2024), April 2026 (Dec 2024). The date when November 2024 was first announced was not verified.

NASA: September 2026

SlippedArtemis

First crewed lunar landing (Artemis III as then defined) in September 2026.

Announced
Original target
September 2026
Current target
February 2028 (NASA: 'early 2028'; month is an approximation)
Months late
Current target is 17 months after the original
Source confidence
Primary or official source checked
Last verified

Interim target: mid-2027 (NASA, Dec 5, 2024 / Jan 30, 2025). Under the Feb 2026 plan the landing mission is now called Artemis IV, 'early 2028'.

NASA: Mid-2027

On trackArtemis

Artemis III as a crewed Earth-orbit test of rendezvous and docking with commercial lander test articles, in 2027 (mid-2027 per NASA architecture update).

Announced
Original target
Mid-2027
Months late
Not applicable
Source confidence
Primary or official source checked
Last verified

Crew named and SLS hardware in processing per NASA. Depends on Starship and/or Blue Moon test articles being ready; neither had flown its propellant-transfer or lander pathfinder milestones as of the evidence date.

In the launch feed

In T-ZERO's current launch feed (about 100 upcoming and a few recent launches), SLS / Artemis matches 0 launches: 0 upcoming and 0 recent.

Counts come from the same Launch Library 2 data as the rest of the site. The feed is a rolling window, so these are not all-time totals.

Other programs

T-ZERO is an unofficial fan project and is not affiliated with NASA. Statuses reflect the cited sources on the verification date.